The plan was to
continue to enlarge the north-west passage. Unfortunately, Tav didn’t make it
today so, neither did the pump. Nick was, sort of, volunteered to bail-out the
pond of his own making. When he got there, Nick was relieved to find the water
level was quite low and it didn’t take long to bail the water out. It was
noticeable that, after a dry week, the drips were not so pronounced. I was back
in the same position as last weekend and managed to get some bags filled and slabs
shifted, not many though as Nick was sending back a steady supply of bags and
rocks. Jon was at the junction, where we had removed the ‘boardwalk’, and was now
clearing away the accumulated detritus that had been around and under it. Alex was
at the bottom of the entrance, hauling away the spoil and loading the skip to
the surface to be pulled up by Jake. Jake had constructed a wooden platform
that straddled the entrance, making it easier underfoot and more stable for his
knee.

Although the
conditions are not ideal at the moment, it was an enjoyable session with a
constant flow of banter and not too much character assassination this morning.
By the end of the session 55 loads had been hauled out to the surface: 35 bags