10th April

Vince, Jake, Brockers, Nick, Tav, Jon, Duncan, and Mike.

A ‘full’ complement of participants today, we split into two groups; one group on the surface consisting of me, Jake and Brockers, the second group underground. The extra pair of hands on the surface enabled spoil heap management to be undertaken and the slope was redistributed. The use of a digging hoe was effective in moving the spoil to pack the space alongside the retaining wall. During sediment movement any stones recovered were added to wall where required.

It was a full-on effort during the morning session with Jake and Brockers rotating the hauling and emptying of bags. About 120 bags and a few skip-loads of rocks were removed from the Soft South out to the spoil heap.

Lunchtime, it was pleasant in the sheltered sunshine.

After break, Mike, Jon and Tav took on the surface duties, me and Brockers were digging, Jake, Nick and Duncan moved the filled bags and sporadic rocks along the passage to the bottom of the entrance, where the spoil was pulled out to the surface. There had been a baulk section between the two areas of digging, this was now mostly removed to allow ease of movement. This had taken-up most of the morning session and part of the afternoon too. The rest of the second session concentrated on expansion. The small fissure in the roof (south-west face) was partially cleared adding a bit more height to the expanding ‘chamber’, lower down, a ‘spread’ of boulders and fragmented calcite is being exposed. Between the boulders appear to be tiny ‘voids’ and the floor seems to be dipping downwards.

Another 120 or so bags and some large rocks were moved up to the surface, the total of loads removed today, about 270, a very productive session. No photos today.