7th December 2019

Vince, Jake, Brockers, Jon, Nick and Tav

Vince set-off to the current end of the Cold Gnarly North with Jake and Brockers to clear the debris from Wednesday evenings application of IRS. Nick, Jon and Tav cleared the rocks still at the Junction/entrance area. There were rather more there than estimated – 46 skip loads out to the surface.

Unfortunately, the IRS didn’t really have the desired effect probably due to the calcite blockage and softer ‘marly’ rock. Even so, there was enough fractured rock that just required loosening some more with bar and hammer. Plenty to occupy three diggers for a while, the result a roomier chamber and an improved ‘skip-run’ for the future. Nick came to find out how we were progressing just as we were deciding to start clearing out the spoil. It didn’t take too long to remove c.25 filled bags and another 8 skip loads of rock out to the surface. A satisfying morning’s work.

A plan has been formulated for the next phase of IRS to be progressed mid-week.