With Jon, Nick and Tav
A reduced team today due to whatever reasons, no matter.
The first task of the day was to replace the hauling rope on the pot pulley system in the deep Soft South. That done, me and Tav digging, rotating the filling of bags, and hauling up the bucket. Jon was on the ledge catching the bucket to un load the contents. Nick was at the junction and shuttling to and from the entrance where the spoil was temporarily stashed. In between loads Nick occupied himself breaking rocks with a hammer.
At the end of the session, 75 bags filled, hauled, and emptied onto the spoil heap plus about two dozen loads of rocks. A reasonably productive session.